Queue management
New queue management power from Ofgem
Ofgem has approved Code Modification CMP376 – Inclusion of Queue Management process within the Connection and Use of System Code (CUSC).
This modification will allow us to proactively manage the connections queue, one of the key components of our five-point plan to speed up grid connections and evolve our network to make it fit for the future, deliver net zero, and keep clean power flowing across Great Britain.
How we’re managing the connections queue
We’re proactively managing the connections queue so customers whose projects are progressing at their contracted rate can connect to the transmission network as quickly as possible.
This is being achieved by terminating contracted projects not progressing against agreed milestones to free-up space for projects which are. This allows us to ensure capacity is fully utilised and projects have the best chance to connect when ready.
Projects that aren’t progressing against agreed milestones will be terminated following Ofgem’s approval of CMP376 – Inclusion of Queue Management process.
Previous webinar material
Watch the slide presentations by pressing the play icon on each image, or download the slides using the link above each image.
Queue Management workshop 1 slides
Download the slides from our first Queue Management webinar on 29 November.
Queue Management workshop 2 slides
Download the slides from our second Queue Management webinar on 5 December.
Queue Management workshop 3 slides
Download the slides from our third Queue Management webinar on 13 December.
Queue Management - Frequently asked questions
Download the Queue Management frequently asked questions document.