CMP448: Introducing a Progression Commitment Fee to the Gate 2 Connections Queue​ 

This proposal establishes a framework to introduce an additional financial requirement on developers, that can be activated if required, to incentivise the timely removal of unviable projects from the connections queue and facilitate the more timely and efficient connection of viable projects. In doing so it will support progress towards clean power by 2030 (“CP30”) and net zero targets.

Modification status:
Current - Workgroup
Last updated:
21 February 2025

Code Administrator Contact: ​​[email protected] 

Governance Route: Urgent modification proceeding under a timetable approved by the Authority (with Authority decision)

Impacts: High Impact on Developers, Generators, Transmission System Operators, Interconnectors, Consumers 

Code modification proposed by:
Ash Adams