CMP343 and CMP340: 'Transmission Demand Residual bandings and allocation for 1 April 2022 implementation (CMP343)' and 'Consequential changes for CMP343 (CMP340)'
CMP343 (formerly CMP332) will deliver part of Ofgem's TCR direction concerning the Transmission Demand Residual (TDR) by creating a methodology by which the residual element of demand Transmission Network Use of System (TNUoS) tariffs can be apportioned to Half Hourly (HH) and Non Half-Hourly (NHH) demand, and a separate methodology to determine the ‘Bands’ against which the residual element of demand TNUoS is levied. CMP340 will provide the definitions required for CMP343.
Code Administrator Contact: Paul Mullen [email protected]
Governance Route: Standard Governance
Implementation: 01 April 2023
Impacts:
CMP343: high impact National Grid ESO, Distribution Network Operators, Suppliers and Demand Users connected to the Transmission Network.
CMP340: low impact All CUSC Users as this will amend Sections other than Section 14 for the purposes of CMP343.
Documents