Organisational, systems and telecoms
Learn about the organisational, systems and telecommunications (OST) workstream, including its objectives and the work it delivered, and download reports relating to its activities.
The OST workstream’s objective
The OST workstream’s objective was to develop the process design, communications and systems required to coordinate all parties involved in an electricity restoration service – also known as black start.
The workstream also sought to highlight changes that would be needed across distributed energy resources (DERs), distribution network operators (DNOs), transmission owners (TOs) and the NESO.
What did the workstream deliver?
The OST workstream specified the requirements for information systems and telecommunications. It highlighted the need for resilience and the challenges of coordinating an electricity system restoration service across many parties.
Engaged stakeholders with desktop exercises
A series of desktop exercises proved valuable in testing the workstream’s proposals. This also allowed a wide cross-section of industry parties to participate and share in project learnings.
Resourcing requirements
Resourcing requirements for DNOs are eased by the introduction of automation.
It’s expected that one DNO control engineer will be capable of managing a single distribution restoration zone (DRZ), including loading the anchor to a stable operating position.
Frequency and voltage control capabilities
Distributed ReStart will be the first process to require voltage and frequency control capability within DNOs under an emergency condition.
The anchor DER will need sufficient engineering resources to meet this requirement within eight hours of instruction (from the lead DNO) to the point of energisation. This also applies to any top‑up service providers from the point of DRZ instruction.
Therefore, it’s essential that training focuses on this specific capability, despite the support received through automation.
Power Engineering and Trials
Find out about the Power Engineering and Trials (PET) workstream’s objectives and what it delivered, and download reports relating to its activities.
Procurement and Compliance
Find out about the objectives and deliverables of the Procurement and Compliance (P&C) workstream, and download reports relating to its activities.
Feasibility studies
Find out about the project’s feasibility studies, the key findings and deliverables, and download reports detailing the outcomes.
Further information
Stay up to date
Join our mailing list for newsletters and updates.
Documents library
Visit our documents library to view our full range of reports.
Get in touch
Email: [email protected] Write: NESO, Faraday House, Warwick Technology Park, Gallows Hill, Warwick, CV34 6DA