CM080: Transmission Impact Assessment Process

DNOs are obliged not to connect any new single embedded generation where it “may have an impact on the NETS” without undertaking a “Request for a Statement of Works” to NGESO.  This process does not take into account the growing trend of smaller embedded generation connections. A “Transmission Impact Assessment” process which facilitates an aggregated assessment process mitigates the need to apply to multiple individual connections saving time/admin and making it easier for NGESO to consider the cumulative impact of smaller individual connections.

Modification status:
Implemented - CM080: Transmission Impact Assessment Process
Last updated:
22 August 2024

Code Administrator Contact: [email protected]

Governance Route: Standard Governance

Impacts: Medium impact on Transmission Owners

Code modification proposed by:
Terry Baldwin

Documents