GC0111: Fast Fault Current Injection specification text
To update the Grid Code and G99 with revised text for fast fault current injection to dispel any confusion in interpretation of the existing text.
Modification status:
Implemented
- GC0111: Fast Fault Current Injection specification text
Last updated:
23 August 2024
This modification was raised by:
Electricity North West in April 2018
The governance route for this modification is:
Standard
The impact of this modification is on:
Manufacturers, installers and owners of Type B to Type D power park modules connected to both distribution and transmission systems.
The modification is currently at:
Implemented
Code modification proposed by:
Mike Kay
Documents