CMP326: Introducing a Turbine Availability Factor' for use in Frequency Response Capacity Calculation for Power Park Modules (PPMs)
To introduce a 'Turbine Availability Factor' into the CUSC to enable accurate calculation by the NGESO Control Centre and consequently accurate settlement of the Frequency Response capability of PPMs when some of the turbines on site are unavailable.
Code Administrator Contact: Paul Mullen - [email protected]
Governance Route: Standard Governance
Implementation: 01 December 2022
Impacts:
* Medium: National Grid Electricity System Operator
* Low: Power Park Module Generators
Documents