PM0128 - Implementation of the Electricity System Restoration Standard
This Modification is proposing a number of changes to the STC Procedures to facilitate Special Condition 2.2 of NGESO’s Transmission Licence. Implementing an Electricity System Restoration Standard (ESRS) which requires 60% of electricity demand to be restored within 24 hours in all regions, and 100% of electricity demand to be restored within 5 days national.
Modification status:
Implemented
- PM0128 - Implementation of the Electricity System Restoration Standard
Last updated:
22 August 2024
Code Administrator Contact: [email protected]
High impacts : on Restoration Service Providers, Generators, Transmission Licensees, Interconnectors, Transmission Owners, Non-Embedded Customers and the Electricity System Operator
Code modification proposed by:
Sade Adenola