PM0126: Transmission Impact Assessment Process in relation to CMP298

This STCP Proposal is DNOs are obliged not to connect any new single embedded generation where it “may have an impact on the NETS” without undertaking a “Request for a Statement of Works” to NGESO. This process does not take into account the growing trend of smaller embedded generation connections which may have a cumulative effect. This Modification seeks to facilitates an aggregated assessment that mitigates the need to assess individual smaller connections making it easier for all parties to get an accurate view of any works required.

Modification status:
Implemented - Concluded
Last updated:
14 June 2024

Code Administrator Contact: Sally Musaka  [email protected]

Governance Route: The Panel will make the decision on whether the modification should be implemented.

Impacts:  Medium impact - Transmission Owners, Transmission System Operators

Code modification proposed by:
Terry Baldwin