GSR020: Modification of Clause 7.8.1.1 to Allow Single Transformer Offshore Substations of Capacity Greater Than 90MW
This working-group shall consider whether the current clauses 7.8.1.1 and 7.13.1.1 and the defined term “Offshore Grid Entry Point (OffGEP) Capacity” should be modified to ensure that the most economic and efficient solutions for the connection of all offshore wind farm connections can be facilitated.
Modification status:
Concluded
- GSR020: Modification of Clause 7.8.1.1 to Allow Single Transformer Offshore Substations of Capacity Greater Than 90MW
Last updated:
20 March 2024