CMP199: Reactive Dispatch Network Restrictions

This modification proposal is a consequential change from the Grid Code Modification E/11 (Reactive Despatch Network Restrictions) which introduces a new definition of a “Reactive Despatch to Zero MVAr Network Restriction” to allow National Grid to despatch such restricted generators providing they can provide zero MVAr.   This CUSC Modification Proposal aligns the CUSC with the Grid Code to allow payments to generators which have a reactive despatch restriction in place whereby they will be paid accordingly if have been despatched by National Grid.

Modification status:
Concluded - CMP199: Reactive Dispatch Network Restrictions
Last updated:
20 March 2024

Code Administrator Contact: Steve Lam - [email protected]

Governance Route: Standard 

Impacts:

* Medium: National Grid Transmission Plc, Industry Parties

Implemented: 3 January 2012