CAP048 - Firm Access and Temporary Physical Disconnection
Where a CUSC party has purchased firm Connection and Transmission Access, NGC will have an obligation to re-purchase these firm rights if they cannot be delivered. An obligation will be included in CUSC which will oblige NGC to purchase CECBMU, and/or TEC Station in response to system needs. When the Transmission System (connection or infrastructure) has a reduced level of availability due to planned or forced outage that results in the temporary physical disconnection of a Generating Unit, NGC will be required buy back CEC and/ or TEC capability from the user via one of two mechanisms:- a) NGC enter into a bi-lateral Transmission Related Agreement (TRA) such that the user has a reduced level of CEC and/or TEC b) NGC buy back from the user CEC and /or TEC capability at a price that is set down in the Connection Charging Methodology and/or the Use of System Charging Methodology. The obligation on NGC to purchase CEC and/or TEC via a) or b) above will be included in the CUSC If NGC purchase CEC and/or TEC via a) the price will be negotiated bilaterally. If NGC purchase CEC and/or TEC via method b) the price and methodology will be set down in the relevant charging methodology.